Malawi Floods ERL: Implementation Completion Report (ICR) Review

Source
World Bank, the

According to the Financing Agreement (p. 5) and the Project Appraisal Document (PAD, paragraph 30), the Project Development Objective (PDO) was "to “sustainably restore agricultural livelihoods, reconstruct critical public infrastructure to improved standards in the flood-affected districts, and improve the Government of Malawi’s disaster response and recovery capacities.” This review will assess project performance against the following objectives:

-To sustainably restore agricultural livelihoods.
-To reconstruct critical public infrastructure to improved standards in the flood-affected districts.
-To improve the Government of Malawi’s disaster response and recovery capacities

Download

Malawi Floods ERL Implementation Completion Report (ICR) Review PDF, 0.2 MB

Last checked: 17 August 2022

Explore further

Hazards Flood
Themes Critical infrastructure Preparedness Livelihood Recovery Recovery planning
Country and region Malawi
Malawi Floods ERL Implementation Completion Report (ICR) Review
Publication year
2021

Also featured on

PreventionWeb

Is this page useful?

Yes No
Report an issue on this page

Thank you. If you have 2 minutes, we would benefit from additional feedback (link opens in a new window).

The International Recovery Platform (IRP) is a global partnership working to strengthen knowledge, and share experiences and lessons on building back better in recovery, rehabilitation, and reconstruction.

Latest IRP videos and photos: YouTube Flickr Contact IRP

Loading